UPDATE: 10/24

Rural Water 3.0 has experienced unexpected delays as the County waited to receive permit approval from the State. Currently, permits have been received for streets in Rural Water 3.1 and 3.3. Permit approval has not yet been received from the State for streets in Rural Water 3.2. Below is an updated timeline.

Rural Water 3.3

  • November: Construction bid request will be released
  • Dec. 2: Recommended construction contractor will be submitted to Fiscal Court for approval
  • Summer 2026: Construction expected to be complete

Once construction contract is signed, the County will provide a more detailed timeline for start dates on specific streets within Rural Water 3.3.

Rural Water 3.1

  • November: Construction bid request will be released
  • Dec. 16: Recommended construction contractor will be submitted to Fiscal Court for approval
  • Summer 2026: Construction expected to be complete

Once construction contract is signed, the County will provide a more detailed timeline for start dates on specific streets within Rural Water 3.2.

Rural Water 3.2

Permit approval has not yet been received from the State.

Rural Water 2.0, which will deliver water to up to 294 homes, is complete. Visit Rural Water 2.0 to learn more.